This project consisted of the renovation of the existing sidewalk pavers for Liberty Mutual Insurance along St. James Ave., Berkeley St., and Stuart St. entrances. McCourt Construction began the work with the demolition of the existing pavers and concrete slab underneath the sidewalk. After the demolition, the site was fine graded and compacted, and gravel was placed in preparation for the concrete pour. Granite pavers were installed by United Stone & Site with McCourt support. Additional improvements included tree grate replacement and meter post installation.

5

McCourt’s project to rehabilitate runway 4R-22L and reconstruct the light pier at this runway is in its final stages. The runway was reopened on schedule and the light pier construction is proceeding apace – all drilled shafts have been completed and pier cap & deck planks are being installed. The completion of the pier is set for the end of August.

4

McCourt Construction along with our joint venture partner Skanska USA Civil is moving into the final stages of the largest of the toll demolition contracts which facilitates the all new electronic tolling system along I-90. Demolition of the toll booths, tunnels and buildings at Exits 9, 10, 10A, 11, 11A, 12 and 13 have been completed. We are currently reconfiguring the ramps which includes drainage, electrical, roadway lighting and roadway treatment work. Scheduled completion of all work is by the end of October 2017.

3

The Runway Status Lights Project just broke ground with in the last week. The new shelter foundation location is being excavated and prepped for concrete work. The horizontal directional drilling has started at night with successful, crossings under Taxiway Kilo for the GilaDuct conduit. Once the conduit gets installed, McCourt will then excavate and backfill conduit trenches along the runways.2

The fence at Eversource’s Substation 447 in Walpole is being erected! After several redesigns, the project has gotten some steam. Eighty-five percent of the fence foundations have been finished while the rest are being formed. McCourt has been erecting the fence with a pace that is better than anyone expected. Once the project is complete, it will be one of two substations in the state with this new fencing system.